A major theme park is expanding the existing facility over a five-year period.

A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.

The following question requires your selection of CCC/CCE Scenario 26 (2.5.50.1.2) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

What class of estimate is used for the preliminary design phase of a project?

A.

Class 5 - order of magnitude estimate with +50% / -30% accuracy

B.

Class 1 - order of magnitude with +30% / -30% accuracy

C.

Class 4 - budget estimate with +30% / -15% accuracy

D.

Class 2 - definitive estimate with +15%/-5% accuracy

AACE International CCP Summary

  • Vendor: AACE International
  • Product: CCP
  • Update on: Aug 21, 2025
  • Questions: 189
Price: $52.5  $149.99
Buy Now CCP PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method