A facility uses 250,000 kWh in a 31-day billing period.

A facility uses 250,000 kWh in a 31-day billing period. The peak demand in the billing period is 1,200 kW. What is the facility partial load factor?

A.

28%

B.

33%

C.

45%

D.

66%

E.

77%