Universal Containers has several independent Salesforce projects this quarter involving shared objects and a complex deployment process managed by a DevOps team. While smoke testing the shared user acceptance testing (UAT) environment, the business analyst (BA) noticed that one of the minor changes to the Account to the Account page layout for the project is missing. The client is eager to begin its UAT.
What should the BA do to address the issue?