You manage a design-build project to renovate a new office space, including infrastructure upgrades.

You manage a design-build project to renovate a new office space, including infrastructure upgrades. At the 60% design phase, the design-build contractor’s project estimate is over budget and contingency. What should be done first to address the issue?

A.

Investigate delaying a portion of the project until additional funding is available.

B.

Pursue a change order from the project sponsor for the difference.

C.

Remove the infrastructure upgrade items from the project scope.

D.

Investigate the reasons for being over budget.

IFMA CFM Summary

  • Vendor: IFMA
  • Product: CFM
  • Update on: Oct 28, 2025
  • Questions: 257
Price: $52.5  $149.99
Buy Now CFM PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method