The IT program manager does not see the value of conducting risk assessments for a...

The IT program manager does not see the value of conducting risk assessments for a new major IT project. The manager is reluctant to cooperate with internal auditors and the newly formed steering committee. Midway through the project, program requirements were changed because the CEO is a friend of a vendor and wants to implement this vendor's new technology. This decision will cause the current IT program budget to be insufficient and will be shown as overspending.

After the requirement change request, the IT program manager should FIRST:

A.

obtain confirmation from the business and a decision by the steering committee.

B.

request additional funding from the business owner to cover the additional scope.

C.

report the matter to internal audit as a program deviation to be reviewed.

D.

align IT with the business and agree to the business request.

Isaca CGEIT Summary

  • Vendor: Isaca
  • Product: CGEIT
  • Update on: Jul 25, 2025
  • Questions: 682
Price: $52.5  $149.99
Buy Now CGEIT PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method