An IS auditor evaluating the change management process must select a sample from the change...

An IS auditor evaluating the change management process must select a sample from the change log. What is the BEST way to the auditor to confirm the change log is complete?

A.

Interview change management personnel about completeness.

B.

Take an item from the log and trace it back to the system.

C.

Obtain management attestation of completeness.

D.

Take the last change from the system and trace it back to the log.

Isaca CISA Summary

  • Vendor: Isaca
  • Product: CISA
  • Update on: Jul 25, 2025
  • Questions: 1407
Price: $52.5  $149.99
Buy Now CISA PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method