Management has learned the implementation of a new IT system will not be completed on time and has requested an audit. Which of the following audit findings should be of GREATEST concern?

A.

The actual start times of some activities were later than originally scheduled.

B.

Tasks defined on the critical path do not have resources allocated.

C.

The project manager lacks formal certification.

D.

Milestones have not been defined for all project products.

Isaca CISA Summary

  • Vendor: Isaca
  • Product: CISA
  • Update on: Jul 25, 2025
  • Questions: 1407
Price: $52.5  $149.99
Buy Now CISA PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method