Management receives information indicating a high level of risk associated with potential flooding near the...

Management receives information indicating a high level of risk associated with potential flooding near the organization's data center within the next few years. As a result, a decision has been made to move data center operations to another facility on higher ground. Which approach has been adopted?

A.

Risk avoidance

B.

Risk transfer

C.

Risk acceptance

D.

Risk reduction

Isaca CISA Summary

  • Vendor: Isaca
  • Product: CISA
  • Update on: Jul 25, 2025
  • Questions: 1407
Price: $52.5  $149.99
Buy Now CISA PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method