Which of the following would be an IS auditor's GREATEST concern when reviewing the early...

Which of the following would be an IS auditor's GREATEST concern when reviewing the early stages of a software development project?

A.

The lack of technical documentation to support the program code

B.

The lack of completion of all requirements at the end of each sprint

C.

The lack of acceptance criteria behind user requirements.

D.

The lack of a detailed unit and system test plan