If an activity time within a critical path is increased, which of the following is...

If an activity time within a critical path is increased, which of the following is most likely to occur?

A.

The project will be delayed.

B.

Additional resources will have to made available.

C.

Costs will increase.

D.

All activities in the project will be affected.