Resource leveling is used to accomplish which of the following objectives?

Resource leveling is used to accomplish which of the following objectives?

A.

Optimizing the use of a project’s workforce

B.

Shortening the length of a project

C.

Determining the resources of a project

D.

Determining peak periods of a project’s workforce overload