Surveys have shown that plants (facilities) with good planning and scheduling systems and good predictive...

Surveys have shown that plants (facilities) with good planning and scheduling systems and good predictive and preventive programs have which ratios of maintenance tasks? (Does not include service to operations or capital projects or turnarounds)

A.

50% of all work is preventive and predictive. 80% of work is planned and scheduled at least one week before execution, 5% of all work is emergency

B.

25% of all work is preventive and predictive. 60% of work is planned and scheduled at least one week before execution, 15% of all work is emergency

C.

95% of all work is preventive and predictive. 90% of work is planned and scheduled at least one week before execution, 5% of all work is emergency

D.

30% of all work is preventive and predictive. 40% of work is planned and scheduled at least one week before execution, 20% of all work is emergency

SMRP CMRP Summary

  • Vendor: SMRP
  • Product: CMRP
  • Update on: Dec 21, 2025
  • Questions: 148
Price: $52.5  $149.99
Buy Now CMRP PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method