The CM is tasked with analyzing the schedule variance of a project on a regular...

The CM is tasked with analyzing the schedule variance of a project on a regular basis. The contractor's recent payment application includes a dramatic increase in earned hours than what was budgeted for the project. This MOST likely indicates

A.

the contractor is making more profit than anticipated.

B.

the project is ahead of schedule.

C.

the contractor will be submitting change orders.

D.

the project is behind schedule.

CMAA Construction-Manager Summary

  • Vendor: CMAA
  • Product: Construction-Manager
  • Update on: Jan 19, 2026
  • Questions: 65
Price: $52.5  $149.99
Buy Now Construction-Manager PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method