JKL, Inc.

JKL, Inc. solicits bids for the repair of a boiler used in its shoe factory. Supplier A submits a bid of $7000. The next lowest bid is $8,000, and the remaining bids are between $10,000 and $11,000. JKL awards the contract to Supplier A. However, before beginning repairs, Supplier A realizes it made a mistake and underestimated the repair work. Supplier A refuses to do the work, saying it would lose money. If JKL declines to increase the payment and claims that Supplier A breached the contract, the MOST likely result would be which of the following?

A.

Supplier A will have breached the contract, but only if JKL did not know or have reason to know that Supplier A's low bid was the result of an error.

B.

Supplier A will not have breached the contract, because Supplier A can successfully argue that the contract is voidable.

C.

Supplier A will not have breached the contract because the frustration of purpose doctrine excuses Supplier A's non-performance.

D.

Supplier A will have breached the contract, but only if it is too late for JKL to accept the bid of the second lowest bidder.

ISM CORE Summary

  • Vendor: ISM
  • Product: CORE
  • Update on: Oct 18, 2025
  • Questions: 312
Price: $52.5  $149.99
Buy Now CORE PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method