PQR’s supply manager signs a contract with Supplier X for delivery of parts totaling $1,250,000 per year for four years. Accompanying the contract is a copy of the organization’s signing policy, which states that supply managers have authority to execute contracts up to $1,000,000 per year. Supplier X questions the discrepancy, but is told verbally by the supply manager that the policy has changed, and supply managers now have a $1,500,000 per year signing limit for up to five years.
Senior management at PQR discovers the supply manager's misstatement and tries to disavow the contract. This attempt will likely be