Weekend Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: xmasmnth

Given the bill of material (BOM) information below and independent requirements of 10 pieces (pcs)...

Given the bill of material (BOM) information below and independent requirements of 10 pieces (pcs) per week of Component A and 20 pieces (pcs) per week of Component B, what is the weekly gross requirement of component F?

A.

80

B.

120

C.

160

D.

200

APICS CPIM-8.0 Summary

  • Vendor: APICS
  • Product: CPIM-8.0
  • Update on: Jul 21, 2025
  • Questions: 150
Price: $52.5  $149.99
Buy Now CPIM-8.0 PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method