Given the bill of material (BOM) information below and independent requirements of 10 pieces (pcs)...

Given the bill of material (BOM) information below and independent requirements of 10 pieces (pcs) per week of Component A and 20 pieces (pcs) per week of Component B, what is the weekly gross requirement of component F?

A.

80

B.

120

C.

160

D.

200