APICS CPIM-8.0 Question Answer
It takes an average of 3 hours to set up a model and 1 hour to run, but depending on the complexity of the models, the setup time can be significantly different. Last week. 2 modelers were working on different projects. Each worked 40 hours. One modeler finished 5 models a day, and the other finished 1 model a day. What was the demonstrated capacity last week?