APICS CPIM-8.0 Question Answer
The question below is based on the following information:
Beginning inventory = 43Week 1Week 2Week 3
Forecast202020
Customer orders221710
Projected on-hand
Master production schedule (MPS)80
Available-to-promise (ATP)
What is the largest customer order that could be accepted for delivery at the end of week 3 without making changes to the master production schedule (MPS)?