An order that moves into a work center on schedule following completion of a previous...

An order that moves into a work center on schedule following completion of a previous operation will move:

A.

to the end of the queue.

B.

to the beginning of the queue.

C.

into the queue in priority sequence.

D.

into the queue when there is capacity available.