GAQM CSM-001 Question Answer
You are the Scrum Master. The Sprint will complete in two days. Each day of the Sprint is equivalent to 8 hours. The team has just enough time to complete all tasks in the remaining 16 hours with the exception of three tasks. Of these three tasks, two tasks (a total of 6 hours) are required to complete one Product Backlog item and one task (an estimate of 2 hours) is required to complete another Product Backlog item. How should the development team handle the remaining three tasks?
GAQM CSM-001 Summary
- Vendor: GAQM
- Product: CSM-001
- Update on: Jan 7, 2026
- Questions: 119

