You are the Scrum Master.

You are the Scrum Master. The Sprint will complete in two days. Each day of the Sprint is equivalent to 8 hours. The team has just enough time to complete all tasks in the remaining 16 hours with the exception of three tasks. Of these three tasks, two tasks (a total of 6 hours) are required to complete one Product Backlog item and one task (an estimate of 2 hours) is required to complete another Product Backlog item. How should the development team handle the remaining three tasks?

A.

The development team should negotiate with the Product Owner on the definition of "done".

B.

The development team should work the extra 8 hours to complete their commitment to the Product Owner

C.

The development team should place the two Product Backlog items back onto the Product Backlog

D.

The development team should keep the three tasks on the Sprint Backlog for the next Sprint and complete those tasks first

GAQM CSM-001 Summary

  • Vendor: GAQM
  • Product: CSM-001
  • Update on: Jan 7, 2026
  • Questions: 119
Price: $52.5  $149.99
Buy Now CSM-001 PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method