When the goal, scope and product domain are not understood by the Scrum Team, the...

When the goal, scope and product domain are not understood by the Scrum Team, the Scrum Master should

A.

Direct the Developers to stop working until the Product Owner improves the acceptance criteria.

B.

Cancel the Sprint and schedule a new Planning meeting.

C.

Do nothing because this is the responsibility of the Product Owner.

D.

Facilitate a discussion between the Stakeholders, Product Owner and Developers.

Scrum Alliance CSM Summary

  • Vendor: Scrum Alliance
  • Product: CSM
  • Update on: Jan 2, 2026
  • Questions: 50
Price: $52.5  $149.99
Buy Now CSM PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method