To increase the likelihood of the success of a software project, the project plan should...

To increase the likelihood of the success of a software project, the project plan should meet which of the following requirements?

A.

It should be completed before the project activities begin.

B.

It should be reviewed and updated at each phase of the project.

C.

It should be developed by an independent software developer

D.

It should be approved by the steering committee.