After completion of the control phase, an improved process must continue to be monitored for...

After completion of the control phase, an improved process must continue to be monitored for which of the following reasons?

A.

One or more of the constraints might move.

B.

The process owner needs time to learn the new process.

C.

It is less costly to improve the process a second time using the same resources.

D.

The next pilot run will address a new constraint.