You have been asked to estimate the testing effort for an upgrade to a legacy...

You have been asked to estimate the testing effort for an upgrade to a legacy product Your team did the testing on the last upgrade, and you have ascertained that this upgrade is about 10% bigger than the last one Given this information which estimation technique should you use to come up with the test effort number?

A.

Function points

B.

Extrapolation

C.

Planning poker

D.

Three-point estimation

ISTQB CTAL-TM Summary

  • Vendor: ISTQB
  • Product: CTAL-TM
  • Update on: Jul 21, 2025
  • Questions: 228
Price: $52.5  $149.99
Buy Now CTAL-TM PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method