ISTQB CTAL-TM Question Answer
You have done a comprehensive risk analysis. You have involved the appropriate people in assessing the risks and determining the likelihood and impact of those risks. You have been testing for three months and have been able to mitigate 75% of the high risk items. You have two weeks left in testing and you now do not expect to be able to complete all the items on the high-risk
mitigation list, never mind any from the medium or low-risk lists.
What is the most effective action you should take? [3]