Upon completion of hardware installation and configuration for a new deployment, the NEXT thing the...

Upon completion of hardware installation and configuration for a new deployment, the NEXT thing the AV Project Manager should have scheduled is

A.

training the client.

B.

testing and verification.

C.

invoicing and project close out.

D.

preventative maintenance schedule.