The correct answers are B, C, and D . In the Implementation Phase, accepted VM proposals must be converted into controlled organizational or project changes. The VM Guide identifies implementation as the phase where the team reviews VM proposals, resolves their disposition, develops an implementation plan, and documents, tracks, and audits results. It also defines an implementation plan as the schedule and action structure needed to implement VM study results, including milestones, tasks, resources, and responsible parties. ( pdfcoffee.com )
For successful change implementation, the guide specifically identifies the appointment of a steering or oversight committee to monitor the change, provide leadership, and resolve conflicts. It also identifies contingency plans to address unanticipated costs, delays, risks, or unforeseen resistance to change. A third required strategy is strong top management commitment to the implementation plan, because leadership support protects the change effort from internal and external challenges and ensures resources remain available through completion. ( pdfcoffee.com )
Option A is related to stakeholder awareness, but the stated implementation strategy is participation and involvement, not merely evaluating concerns. Option E is incorrect because broad large-group decision-making can slow resolution; VM emphasizes key stakeholder involvement and controlled governance.
References/topics: Implementation Phase; Change Management; Implementation Plan; Steering/Oversight Committee; Resistance to Change.