The correct answers are A, D, and E . A “conditionally accepted” VM proposal is not rejected, but it is also not fully approved for immediate implementation. It requires follow-up before final acceptance. Therefore, the Implementation Meeting documentation must clearly record what action is required , who is responsible , and when the final decision will be made .
This aligns directly with SAVE’s VM Job Plan logic. The Development Phase requires the team to prepare implementation requirements, including initial cost, life-cycle cost, implementation cost, risk, uncertainty, and schedule impact. It also requires an implementation plan containing the proposed schedule, team assignments, and management requirements. ( UW Courses ) The Presentation Phase then seeks concurrence and commitment from management, and the written report confirms the implementation plan accepted by management. ( UW Courses ) During Post-Study, assignments are made to complete tasks associated with the approved implementation plan. ( UW Courses )
Grammar changes are editorial, not implementation-control information. VM team disagreements may be noted internally if relevant, but they are not the typical required record for conditional acceptance.
References/topics: Implementation Phase; Presentation Phase; Post-Study Activities; Implementation Plan; VM Proposal Follow-Up.