Question:
A Fibre Channel switch has eight ports, and all ports must be operational from 6 AM to 6 PM, Monday through Friday. However, a failure of Port 4 occurs within the week as follows:
Monday: 11 AM to 1 PM
Wednesday: 5 PM to 10 PM
Thursday: 7 AM to 10 AM
Saturday: 11 AM to 1 PMWhat is the availability of Port 4 in that week?