When constructing a new data center, what is a best practice for controlling the influence of outside humidity?

A.

Use water-based paints for the walls.

B.

Install vapor barriers in walls and around doors.

C.

Increase the number of doors leading out of the data center.

D.

Use 2 foot by 6 foot ( .61 meters by 1.83 meters) steel framing for the walls, floors, and ceilings.