CIMA E2 Question Answer
A project manager is calculating the budget cost of a single project task called "Server Configuration".
This task is estimated to last 8 weeks and requires the full-time services of two software consultants, both for the entire duration of the task.
One consultant commands an inclusive rate of $400/day and the other $40/hour based on an eight hour day. Fixed hardware costs of $12,000 have also been estimated for the task.
Calculate the total budget cost for the task (ignoring any other resources or costs) - assuming a five day working week.
Give your answer as a whole number.
The total cost is $ .
CIMA E2 Summary
- Vendor: CIMA
- Product: E2
- Update on: Dec 16, 2025
- Questions: 210

