A project manager is calculating the budget cost of a single project task called "Server...

A project manager is calculating the budget cost of a single project task called "Server Configuration".

 

This task is estimated to last 8 weeks and requires the full-time services of two software consultants, both for the entire duration of the task.

One consultant commands an inclusive rate of $400/day and the other $40/hour based on an eight hour day. Fixed hardware costs of $12,000 have also been estimated for the task.

 

Calculate the total budget cost for the task (ignoring any other resources or costs) - assuming a five day working week.

 

Give your answer as a whole number.

 

The total cost is $    .

CIMA E2 Summary

  • Vendor: CIMA
  • Product: E2
  • Update on: Dec 16, 2025
  • Questions: 210
Price: $52.5  $149.99
Buy Now E2 PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method