There are several techniques that can be used when planning a project.

There are several techniques that can be used when planning a project. Which of the following best describes a Work Breakdown Structure?

A.

A technique which can be used with critical path analysis to deal with uncertainties and risk within the project.

B.

A set of documents identifying each stage and task to be performed during development, defining a hierarchy of work prior to the allocation of tasks.

C.

A method of scheduling tasks using a chart on which bars represents the relative length of the task.

D.

A technique to arrange activities required to achieve the project objective, agreeing the objectives and determining exactly  the project aims.

CIMA E2 Summary

  • Vendor: CIMA
  • Product: E2
  • Update on: Dec 15, 2025
  • Questions: 210
Price: $52.5  $149.99
Buy Now E2 PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method