A team selects a Product Backlog Item (PBI) for the Sprint Backlog.

A team selects a Product Backlog Item (PBI) for the Sprint Backlog.

What must a team do to finish the Product Backlog Item it selects?

A.

As much as can be done in the Sprint before the deadline.

B.

As much as is required to satisfy the definition of 'done'.

C.

Analyze, design, program, test and document the PBI.