For a Sprint, progress is monitored in a burn-up chart with bars.

For a Sprint, progress is monitored in a burn-up chart with bars.

What makes the bar become longer?

A.

The progression of time.

B.

Work is added to the Sprint Backlog.

C.

Work is deleted from the Sprint Backlog.