CD commenced a construction contract on 1 April 20X9.

CD commenced a construction contract on 1 April 20X9.  The contract value was agreed at $100,000. CD had incurred $40,000 costs to date and estimated costs to completion were $50,000.  At the year ended 31 December 20X9 this contract was estimated to be 60% complete.   CD adopted the provisions of IAS 11 Construction Contracts when preparing its financial statements for the year to 31 December 20X9.

What value should be included in CD's profit for the year ended 31 December 20X9 in respect of this contract?  

Give your answer to the nearest whole number.

$ ?  

CIMA F2 Summary

  • Vendor: CIMA
  • Product: F2
  • Update on: Jul 29, 2025
  • Questions: 268
Price: $52.5  $149.99
Buy Now F2 PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method