Eric is the project manager of the NQQ Project and has hired the ZAS Corporation...

Eric is the project manager of the NQQ Project and has hired the ZAS Corporation to complete part of the project work for Eric's organization. Due to a change request the ZAS Corporation is no longer needed on the project even though they have completed nearly all of the project work. Is Eric's organization liable to pay the ZAS Corporation for the work they have completed so far on the project?

A.

Yes, the ZAS Corporation did not choose to terminate the contract work.

B.

It depends on what the termination clause of the contract stipulates.

C.

It depends on what the outcome of a lawsuit will determine.

D.

No, the ZAS Corporation did not complete all of the work.

GIAC GSLC Summary

  • Vendor: GIAC
  • Product: GSLC
  • Update on: Dec 24, 2025
  • Questions: 567
Price: $52.5  $149.99
Buy Now GSLC PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method