You are the project manager of a large project that will span several time zones.

You are the project manager of a large project that will span several time zones. You'll be utilizing project team members from across several departments. Project team members won't be working on the project full-time and will join and leave the project based on assignments in the project schedule.

What project management plan can you create to help you manage when project times will be brought onto and released from the project team?

A.

Staffing management plan

B.

Team management plan

C.

Project management plan

D.

Human resources management plan

GIAC GSLC Summary

  • Vendor: GIAC
  • Product: GSLC
  • Update on: Dec 24, 2025
  • Questions: 567
Price: $52.5  $149.99
Buy Now GSLC PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method