GIAC GSLC Question Answer
You are working in a functional organization and are managing the IHH Project. Your project will likely last for six months and has a budget constraint of $1,876,000. You'll be dealing with a functional manager to manage costs and resources in the project. Who will have authority over assigning the project team members to activities?