Exact Extract — Huawei V3.0 Training Material, PDF Page 422
Do not perform POC tests in the production environment that has been delivered to the customer.
They must obtain a written disclaimer from the customer before accessing the production network.
Huawei storage POC activities must be planned to minimize operational risks, particularly when tests could affect a customer's production infrastructure.
Option A describes the required risk-control approach. POC devices should not ordinarily be connected to live production services. If production access is explicitly required, customer authorization and a written disclaimer must be obtained before proceeding.
The test scope, expected risks, technical responsibilities, and rollback requirements should be established in advance.
Option C covers equipment lifecycle management. POC devices should be tracked, collected, and returned according to the agreed process after testing is completed.
Option D addresses operational coordination. Technical issues, customer requirements, observed risks, and test results must be communicated promptly and followed through to resolution.
Option B is unacceptable as written.
Being familiar with the production environment does not authorize test personnel to log in to customer production switches or make network changes.
Any changes to production infrastructure require explicit customer authorization, approved change procedures, and appropriate operational controls.
Unauthorized configuration changes could interrupt production services or create security vulnerabilities.
Therefore, A, C, and D are correct.