Which of the following is true regarding risk analysis?

Which of the following is true regarding risk analysis?

A.

Impact and likelihood should be assessed together.

B.

Impact and likelihood should be given equal consideration by the internal auditor.

C.

Impact and likelihood should be measured using quantitative methods.

D.

Impact and likelihood should be used to determine risk response.