An internal auditor is assigned to an advisory engagement for the launch of a new system relating to travel and expense. During fieldwork, the auditor tests interfacing controls with the procurement system. The auditor observes that a key control is missing within the procurement system. The auditor identifies that senior management has approved a temporary manual workaround for the missing control. Which of the following actions should the auditor take?