A team member is not performing well on the project because she is inexperienced in...

A team member is not performing well on the project because she is inexperienced in system development work. There is no one else available who is better qualified to do the work.

What is the BEST solution for the project manager?

A.

Consult with the functional manager to determine project completion incentives for the team member.

B.

Obtain a new resource more skilled in development work.

C.

Arrange for the team member to get training.

D.

Allocate some of the project schedule reserve.

BCS ISEB-PM1 Summary

  • Vendor: BCS
  • Product: ISEB-PM1
  • Update on: Jul 27, 2025
  • Questions: 625
Price: $52.5  $149.99
Buy Now ISEB-PM1 PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method