Which may be employed to shorten a schedule without changing the scope of the task?

Which may be employed to shorten a schedule without changing the scope of the task?

A.

Alter to task priorities.

B.

Releasing resources earlier from tasks which were scheduled with a late start.

C.

Fast tracking or Crashing

D.

Fast tracking.

E.

Crashing