While creating the agenda for a status meeting with the team, a project manager receives...

While creating the agenda for a status meeting with the team, a project manager receives input from one team member that an item should be added. Another team member says the team is not ready to resolve the item during the meeting. After much discussion, the project manager decides to put the item on the agenda as an initial discussion item only.

Which conflict resolution technique is the project manager using?

A.

Compromise

B.

Smoothing

C.

Forcing

D.

Withdrawal

BCS ISEB-PM1 Summary

  • Vendor: BCS
  • Product: ISEB-PM1
  • Update on: Jul 27, 2025
  • Questions: 625
Price: $52.5  $149.99
Buy Now ISEB-PM1 PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method