Which of the following would be the MOST appropriate thing to do during the monitoring...

Which of the following would be the MOST appropriate thing to do during the monitoring and controlling process group?

A.

Implement recognition and reward systems.

B.

Obtain sign-off of the product of the project.

C.

Issue performance reports.

D.

Keep everyone focused on completing the project to the charter.