Which of the following would most likely increase the accuracy of estimating the project cost?

Which of the following would most likely increase the accuracy of estimating the project cost?

A.

Using historical data.

B.

Pricing out the work at lower levels in the work breakdown structure.

C.

Both 1) Pricing out the work at lower levels in the work breakdown structure, and 2) Talking to people who have worked on similar projects.

D.

Talking to people who have worked on similar projects.

E.

1) Pricing out the work at lower levels in the work breakdown structure, and 2) Talking to people who have worked on similar projects, and 3) Using historical data.

BCS ISEB-PM1 Summary

  • Vendor: BCS
  • Product: ISEB-PM1
  • Update on: Jul 27, 2025
  • Questions: 625
Price: $52.5  $149.99
Buy Now ISEB-PM1 PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method