You are a project manager for an engineering company.

You are a project manager for an engineering company. Your company won the bid to add ramp-metering lights to several on-ramps along a stretch of highway at the south end of the city. You subcontracted a portion of the project to another company. The subcontractor's work involves digging the holes and setting the lamp poles in concrete. The subcontractor's performance is not meeting the contract requirements.

Which of the following is not a valid option?

A.

You document the poor performance in written form and send the correspondence to the subcontractor.

B.

You terminate the contract for poor performance and submit a change request through Contract Administration.

C.

You agree to meet with the subcontractor to see whether a satisfactory solution can be reached.

D.

You submit a change request through Contract Administration demanding that the subcontractor comply with the terms of the contract.

BCS ISEB-PM1 Summary

  • Vendor: BCS
  • Product: ISEB-PM1
  • Update on: Jul 27, 2025
  • Questions: 625
Price: $52.5  $149.99
Buy Now ISEB-PM1 PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method