You are a project manager for the Swirling Seas Cruises food division.

You are a project manager for the Swirling Seas Cruises food division. You're considering two different projects regarding food services on the cruise lines. The initial cost of Project Fish'n for Chips will be $800,000, with expected cash inflows of $300,000 per quarter. Project Picnic's payback period is six months.

Which project should you recommend?

A.

Project Fish'n for Chips, because the costs on Project Picnic are unknown.

B.

Project Picnic, because Project Fish'n for Chips' payback period is two months longer than Project Picnic's.

C.

Project Picnic, because Project Fish'n for Chips' payback period is four months longer than Project Picnic's.

D.

Project Fish'n for Chips, because its payback period is two months shorter than Project Picnic's.

BCS ISEB-PM1 Summary

  • Vendor: BCS
  • Product: ISEB-PM1
  • Update on: Jul 27, 2025
  • Questions: 625
Price: $52.5  $149.99
Buy Now ISEB-PM1 PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method