You have been nominated as audit team leader for the second recertification to ISO 14001 of ABC, a public transport organisation in a big city. The audit is planned to take place in two months.
The audit program manager asks you to review the answer provided by ABC to a nonconformity raised by another auditor during the last surveillance audit carried out eight months ago.
The nonconformity reads as follows:
*“ABC does not always communicate its relevant environmental requirements to external providers. Evidence: A two-month contract signed with a new external provider of the maintenance for ABC’s buses did not contain any relevant environmental requirements.”*
Which two would you consider to be the best corrective actions from ABC?