Scenario:NexTech Innovations, a dynamic tech startup located in Seoul, South Korea, is renowned for its...

Scenario:

NexTech Innovations, a dynamic tech startup located in Seoul, South Korea, is renowned for its advancements in artificial intelligence and robotics. Serving a global clientele, NexTech encountered a sudden obstacle when a critical supplier abruptly ceased operations, disrupting their supply chain and threatening their ability to deliver products on schedule. Recognizing the need for resilience, NexTech initiated the implementation of a robust business continuity management system (BCMS) based on ISO 22301.

NexTech's top management established a project team of five members and appointed Rebecca, the lead operations manager, as the project manager. The BCM team was tasked with the effective implementation of the BCMS in line with ISO 22301 requirements. Rebecca worked with the top management to analyze the internal context of the company to define the BCMS scope, focusing on assessing and determining who is responsible for coordinating and managing activities at different organizational levels.

The project team divided the implementation project into smaller tasks, identifying the personnel, equipment, and materials needed for each. Rebecca personally handled resource allocation to implement and support the BCMS. Meanwhile, the top management ensured active involvement and commitment at all levels of the organization to enhance the BCMS's effectiveness.

Rebecca and the team drafted and published the business continuity policy on the company’s website. However, some employees found the technical jargon challenging to understand, so comprehensive training sessions were held to address this issue. These measures strengthened NexTech’s resilience and enhanced client trust by proactively addressing potential disruptions.

Rebecca allocated the necessary resources for implementing and supporting the BCMS. Is this in compliance with ISO 22301?

A.

Yes, it is the project manager's responsibility to allocate resources for the management system.

B.

No, resource allocation for the BCMS should be delegated to a resource allocation team, not the project manager alone.

C.

No, it is the top management’s responsibility to allocate the resources needed for the BCMS.

PECB ISO-22301-Lead-Implementer Summary

  • Vendor: PECB
  • Product: ISO-22301-Lead-Implementer
  • Update on: Jul 22, 2025
  • Questions: 80
Price: $52.5  $149.99
Buy Now ISO-22301-Lead-Implementer PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method